Series C LLC Rezoning at South Freeway
View full legal title
(CD 9) Series C LLC, A Series of Diamond Creek Investments LLC / FC Designs; 5051 South Freeway, (8.47 acres) From: "E" Neighborhood Commercial, "I" Light Industrial, and "J" Medium Industrial To: "I" Light Industrial (Recommended for Approval by the Zoning Commission)(Continued from a Previous Meeting)
Get notified on new hearings, votes, or status changes for this matter.
Actions
Showing all 3 actions. Filter by: , , .
Confirm Texas appeal deadline for South Freeway rezoning
Context: City Council approved ZC-25-208 on April 28, 2026 by a 10-0 vote; the statutory challenge window under Texas LGC §211.011 runs 10 days from that date, placing the deadline on or around May 8.
Recommended: Determine immediately whether the 10-day certiorari window under Texas Local Government Code §211.011 has already closed — if any client wants to challenge this rezoning, the deadline runs from April 28 and may have expired. For applicant's counsel, confirming closure clears the way to advise on construction financing commitments without challenge risk.
Verify adopted ordinance conditions for South Freeway rezoning before site planning
Context: ZC-25-208 was continued from March 10 to April 28 before its unanimous approval; continuances in this posture frequently produce conditions that appear in the ordinance but not in the motion summary, and those conditions govern site plan approval.
Recommended: Request the adopted ordinance text from Fort Worth's City Secretary now and compare the exact language of Council Member Beck's April 28 motion against any written conditions in the ordinance itself — the 7-week continuance from March 10 is the window when conditions are typically negotiated into the record, and those terms are binding on construction regardless of what appeared in pre-application discussions.
Investigate who controls Series C LLC behind South Freeway data center rezoning
Context: The March 10, 2026 City Council minutes noted three CD 8 rezonings totaling approximately 120 acres of proposed industrial and data center development were all continued together; this case and presumably the others moved in lockstep, suggesting a single program behind multiple docket numbers.
Recommended: Pull Texas Secretary of State corporate records for Series C LLC and cross-reference the principals against the other two large-acreage CD 8 rezonings that were continued alongside this case on March 10 — if common ownership or investors appear across multiple cases, a coordinated 120-acre land assembly may be underway that was never disclosed in individual docket filings.
Key Entities
View relationship map
Loading relationship map…
Trust Proof
What we said then vs what happened next
We said (Apr 23, 2026):
Contact Council Member Beck to re-schedule South Freeway rezoning
What happened (Apr 28, 2026):
Approved
We said (Apr 23, 2026):
Request April 28 minutes for undocumented South Freeway rezoning continuance
What happened (Apr 28, 2026):
Approved
We said (Apr 23, 2026):
Assess mandamus risk on stalled South Freeway rezoning
What happened (Apr 28, 2026):
Approved
Timeline
Council Member Beck made a motion, seconded by Council Member Nettles, that Zoning Docket ZC-25-208 be approved. Motion passed 10-0, Council Member Lauersdorf off the dais.
(CD 9) Series C LLC, A Series of Diamond Creek Investments LLC / FC Designs; 5051 South Freeway, (8.47 acres) From: "E" Neighborhood Commercial, "I" Light Industrial, and "J" Medium Industrial To: "I" Light Industrial (Recommended for Approval by the Zoning Commission)(Continued from a Previous Meeting)
Vote: 10 for, 0 against, 1 absent
continue to April 28, 2026 Council meeting