Zoning Commission · 12:00 PM · City Hall, 100 Fort Worth Trail, Fort Worth 76102
Analysis based on the published agenda — official vote outcomes not yet available. Check the minutes for vote results.
Matters
Joe Passanisi Concrete Batch Plant at 3800 Deen Road (ZC-25-185)
Showing all 4 actions. Filter by: , , , .
File Deen Road batch plant denial appeal before deadline
Context: Texas law gives zoning applicants approximately 30 days from final council action to appeal to district court; the denial was recorded June 9, 2026, and the two prior continuances (March 10 and April 28) show the council had multiple opportunities to accept conditions yet declined every time — a pattern that shapes both the strength and the theory of any appellate claim.
Recommended: Pull the June 9 council minutes to determine whether the council stated specific findings supporting the 11-0 denial, then assess appellate grounds and file a district court petition before the statutory window closes — after three hearings and two continuances, the record likely contains the council's full stated rationale and any conditions the applicant attempted but failed to negotiate.
Check if Deen Road site qualifies under new residential zoning reform
Context: The June 9 Fort Worth council session simultaneously denied ZC-25-185 11-0 and adopted a reform explicitly opening every commercial district to multifamily and mixed-use residential, creating an alternative development path for this site that did not exist 24 hours earlier.
Recommended: Confirm whether 3800 Deen Road's existing base zoning is commercial — if so, the citywide zoning reform adopted on June 9 (the same session that denied ZC-25-185) now allows multifamily and mixed-use residential by right, letting you pivot to a residential project without filing a new zoning case or waiting out the 2-year refiling restriction that applies if you reattempt industrial use.
Request Deen Road batch plant staff reports from all three hearings
Context: ZC-25-185 appeared before council three times over three months; the March 10 vote bypassed a formal roll call (recorded in the meeting data as 'by consensus, no formal roll call vote'), and the June 9 denial was unanimous 11-0 after Mayor Pro Tem Flores made the motion — a trajectory suggesting the applicant could not address objections that were never publicly articulated on the record.
Recommended: File a public records request for the staff reports, applicant-submitted materials, and any written conditions proposed at the March 10, April 28, and June 9 hearings to find out what concessions — if any — were negotiated during two continuances that still produced an 11-0 denial; pay particular attention to whether staff recommendations shifted across sessions and flag that the March 10 continuation was handled by consensus with no formal roll call, an unusual procedural choice for a contested industrial zoning case.
Verify if Deen Road site can now be developed as apartments without a public vote
Context: The June 9 council session denied ZC-25-185 11-0 and simultaneously adopted a reform opening all Fort Worth commercial districts to multifamily and mixed-use residential; residents who showed up to oppose a concrete batch plant may not have seen the accompanying policy change that affects what can replace it.
Recommended: Residents near 3800 Deen Road who opposed the concrete batch plant should check the parcel's current base zoning against the citywide reform passed the same June 9 night — if the site is commercially zoned, apartments or mixed-use development could now proceed by right with no public hearing and no council vote required, meaning the industrial threat is removed but a different type of significant development could arrive without the notice a zoning case would trigger.
PD Amendment ZC-26-004
Showing all 3 actions. Filter by: , , .
Confirm redesign application meets new dual rezoning notice requirements
Context: Council adopted the new dual-notice requirements at the same session it denied ZC-26-004 11-0 on May 12, 2026, making them effective for any subsequent application on this corridor.
Recommended: The May 12 session updated rezoning notice procedures to require both web publication and a physical sign posting — any redesign application for this corridor must satisfy both requirements or risk a procedural challenge that could reset the entire timeline. Review the adopted text amendment before advising the client to refile.
Check if Small Lot Housing now permits corridor development without new rezoning
Applies if: Site or adjacent corridor parcels include one-family zoning districts
Context: Council denied ZC-26-004 11-0 and adopted the Small Lot Housing text amendment at the same May 12, 2026 session, creating an alternative path that did not exist the day before.
Recommended: Pull the citywide text amendment adopted at the same May 12 session that added Small Lot Housing as a permitted use in all one-family districts under Texas LGC Chapter 211 Subchapter D — if this corridor includes one-family zoned parcels, that path may allow development without a new PD application and bypasses the 2-year restriction triggered by the ZC-26-004 denial.
Request staff reports explaining the two-month delay then unanimous denial
Context: ZC-26-004 was continued March 10 (10-0 consensus, no roll call) and denied May 12 (11-0 formal vote) with Council Members Nettles and Peoples leading the motion — the gap between these two actions is unexplained in the available record.
Recommended: Pull the staff reports from both the March 10 continuation and the May 12 denial — the matter was held two months by 10-0 consensus with no stated reason in the minutes, then denied 11-0, and the public record does not explain what changed between those two votes. Compare the two reports for any shift in staff recommendation, opposition volume, or applicant design modifications.
Lohaliva Commercial Zoning at Dan Danciger Road (ZC-25-212)
Showing all 3 actions. Filter by: , , .
Verify no protest petition clouds Dan Danciger commercial rezoning
Context: The March 10, 2026 vote was 10-0 with Mayor Parker absent; if a protest petition covered 20 percent or more of adjacent area, the statutory supermajority requirement applies and must be confirmed in the record before the approval is treated as unassailable.
Recommended: Confirm with Fort Worth's City Secretary whether any adjacent landowner filed a written protest before the March 10 hearing — if a qualifying protest was filed, Texas Local Government Code §211.006 required a three-fourths council vote, and you must verify the 10-member tally satisfies that threshold before advising your client to commit capital.
Pull adopted ordinance for Dan Danciger Road commercial rezoning
Context: ZC-25-212 was continued 9-0 on Feb 24, 2026, then approved 10-0 on Mar 10, 2026; the gap between those two votes is where conditions are typically negotiated and recorded in the adopting ordinance.
Recommended: Request the enrolled ordinance text from Fort Worth's City Secretary to identify any conditions attached to this approval before submitting site plans or executing construction contracts — a mid-process continuance from Feb 24 to Mar 10 frequently signals staff-negotiated conditions that restrict permitted uses or require on-site improvements beyond what the zoning map alone shows.
Explain Council Member Beck's role in Lohaliva Dan Danciger approval
Context: The Feb 24 continuance vote listed Beck as absent (Motion passed 9-0, Council Members Nettles and Beck were absent), yet Beck is named as the motion-maker for the 10-0 approval on March 10, 2026.
Recommended: Cross-reference Lohaliva's Texas Secretary of State entity registration against Council Member Beck's district boundaries and campaign finance records — Beck was absent when this case was continued Feb 24 but personally made the approval motion March 10, and the public record offers no explanation for that shift.
Series C LLC Rezoning at South Freeway (ZC-25-208)
Showing all 3 actions. Filter by: , , .
Confirm Texas appeal deadline for South Freeway rezoning
Context: City Council approved ZC-25-208 on April 28, 2026 by a 10-0 vote; the statutory challenge window under Texas LGC §211.011 runs 10 days from that date, placing the deadline on or around May 8.
Recommended: Determine immediately whether the 10-day certiorari window under Texas Local Government Code §211.011 has already closed — if any client wants to challenge this rezoning, the deadline runs from April 28 and may have expired. For applicant's counsel, confirming closure clears the way to advise on construction financing commitments without challenge risk.
Verify adopted ordinance conditions for South Freeway rezoning before site planning
Context: ZC-25-208 was continued from March 10 to April 28 before its unanimous approval; continuances in this posture frequently produce conditions that appear in the ordinance but not in the motion summary, and those conditions govern site plan approval.
Recommended: Request the adopted ordinance text from Fort Worth's City Secretary now and compare the exact language of Council Member Beck's April 28 motion against any written conditions in the ordinance itself — the 7-week continuance from March 10 is the window when conditions are typically negotiated into the record, and those terms are binding on construction regardless of what appeared in pre-application discussions.
Investigate who controls Series C LLC behind South Freeway data center rezoning
Context: The March 10, 2026 City Council minutes noted three CD 8 rezonings totaling approximately 120 acres of proposed industrial and data center development were all continued together; this case and presumably the others moved in lockstep, suggesting a single program behind multiple docket numbers.
Recommended: Pull Texas Secretary of State corporate records for Series C LLC and cross-reference the principals against the other two large-acreage CD 8 rezonings that were continued alongside this case on March 10 — if common ownership or investors appear across multiple cases, a coordinated 120-acre land assembly may be underway that was never disclosed in individual docket filings.
SUP ZC-26-005
11 items
AI-generated summaries. Click to expand for original text.
#D.1Zoning change for a 4-acre site at 3800 Deen Road, keeping K Heavy Industrial zoning but adding a Conditional Use Permit for a concrete batch plant, with site plan included.
#D.2Zoning change for 8.47 acres at 5051 South Fwy from E Neighborhood Commercial, I Light Industrial, and J Medium Industrial to I Light Industrial.
#D.3Zoning change request for 0.18 acres at 2104 R.W. Bivens Lane from Urban Residential to One-Family within the Stop Six Overlay.
#D.4Zoning change request for 0.3 acres at 5904 & 5908 Etsie Street from Agricultural to General Commercial Restricted.
#D.5Zoning change request for 0.97 acres at 6605 Dan Danciger Road from Community Facilities to Neighborhood Commercial Restricted; to be heard by City Council on February 24th.
#D.6Zoning change for 0.21 acres at 120 Riverside Drive & 3115 Chenault Street to Neighborhood Commercial and Neighborhood Commercial Restricted with a three-year Conditional Use Permit for retail sales and a hydraulic shop, plus multiple development waivers.
#D.7Zoning change request for 5.27 acres at 5621 Parker Henderson Road from two-family residential and light industrial to light industrial, with a Conditional Use Permit for an electrical substation.
#D.8Zoning change request for 39.6 acres at 5810 Oak Grove Road from A-5 One-Family to AR One-Family Restricted and PD/I Planned Development for light industrial uses with exclusions; site plan waiver requested.
#D.9Zoning change request for 7.12 acres at 4001 Ohio Garden Road from PD69/PD-SU temporary vehicle storage to PD/I light industrial with exclusions and development standard variations; site plan included.
#D.10Zoning change request for 0.73 acres at 5139 Camp Bowie Road from F General Commercial to PD/E Planned Development with reduced landscaping and 59 fewer parking spaces; case will be continued to the March 11, 2026 meeting.
#D.11Zoning change request for 0.16 acres at 2928 Burton Ave from PD1342 planned development (neighborhood commercial uses) to A-5 One-Family.
Municue is in beta
We're building the most comprehensive municipal intelligence platform. Your feedback shapes what we build next.