Application to replat a 0.5308-acre tract on Hull Avenue (south of Linfield Road) into three 0.1769-acre residential lots; staff recommends approval subject to conditions.
…38 to create three 0.1769-acre (7,708-square foot) lots, on property located on Hull Avenue, south of Linfield Road. Applicant/Owner: AAAA Plus Surveyors, LLC Surveyor:…
January 2026
Authorizes a $498,025 increase to the construction services contract with Estrada Concrete Company, LLC for additional storm drainage improvements on Hull Avenue as part of the Joppa Infrastructure Improvements project, bringing the total contract to $6,220,960, financed by CDBG Reprogramming funds.
Authorize an increase in the construction services contract with Estrada Concrete Company, LLC for the additional storm drainage improvements needed on Hull Avenue from 300 feet South of Linfield Road