Spring Avenue
location
1 mention across 1 event
1 eventLast active Tracked since $1.2M city spending
Topics
contract (1)
transportation (1)
Roles
mentioned (1)
Related Entities
View network map
Loading network map…
Activity Timeline
February 2026
Consent Agenda
Authorizes a contract increase with Tiseo Paving Company to cover site security during work suspension, demobilization, remobilization, and additional work units needed to complete the Dolphin Road reconstruction, raising the contract ceiling from $7.17M to $8.38M.
…e additional work units necessary to complete the project for Dolphin Road from Spring Avenue to North of Haskell Avenue/Military Parkway - Not to exceed $1,208,927.02, from…
$1.2M