Municue

Spring Avenue

location
1 mention across 1 event
1 eventLast active Tracked since $1.2M city spending

Topics

contract (1)
transportation (1)

Roles

mentioned (1)
View network map

Loading network map…

Activity Timeline

February 2026

Consent Agenda

Authorizes a contract increase with Tiseo Paving Company to cover site security during work suspension, demobilization, remobilization, and additional work units needed to complete the Dolphin Road reconstruction, raising the contract ceiling from $7.17M to $8.38M.

…e additional work units necessary to complete the project for Dolphin Road from Spring Avenue to North of Haskell Avenue/Military Parkway - Not to exceed $1,208,927.02, from…

$1.2M