Kay Bailey Hutchison Convention Center Dallas Master Plan

project
20 mentions across 14 events

Also known as: KBHCCD, KB Master Plan

The Kay Bailey Hutchison Convention Center Dallas Master Plan is a comprehensive expansion and redevelopment initiative for the convention center and its surrounding downtown area. The plan proposes creating a walkable, mixed-use district with improved street networks that reconnect downtown with adjacent neighborhoods. The redesigned facility is intended to enhance convention capacity and serve as a catalyst for economic development and tourism.
14 eventsLast active Tracked since $1.0B city spending

Mention Frequency

Topic Distribution

Topics

development (14)
contract (11)
budget (5)
items for individual consideration (4)
passed (3)
transportation (3)
financial (3)
bond (2)
grant (2)
governance (2)

Roles

mentioned (20)

Connected Matters

Legislative threads where Kay Bailey Hutchison Convention Center Dallas Master Plan is mentioned

Location

650 South Griffin Street, Dallas, TX 75202·Show on Google Maps ↗
View network map

Loading network map…

Activity Timeline

March 2026

Items For Further Consideration

Authorizes an economic development grant agreement with Dallas Wings Development LLC to construct a sports facility on city-owned park property at 1200 North Cockrell Hill Road (up to $57.9M), amends the Dallas Memorial Auditorium resident use agreement with Full Court Partners LLC dba Dallas Wings, and reduces the McKissack and McKissack project management contract by $1.85M to eliminate the Dallas Wings Practice Facility from scope.

…tee on Professional Sports Recruitment and Retention) *In alignment with the Kay Bailey Hutchison Convention Center Dallas Master Plan. hana.briefki@dallascityhall.com

$56.0M

February 2026

Items For Individual Consideration

Authorize Supplemental Agreement No. 2 to the professional services contract with Perkins & Will, Inc. for additional architectural and engineering services for the KBHCCD Convention Center Expansion West of Lamar, increasing the contract by $3,045,443.45 to a new total of $144,619,808.45.

…9,808.45 - Financing: CCT Revenue Bonds, Series 2023 Fund *In alignment with Kay Bailey Hutchison Convention Center Dallas Master Plan. jesse.saldana@dallascityhall.com

$3.0M
Items For Individual Consideration

Authorizes an economic development grant agreement with Dallas Wings Development LLC to construct a facility on city-owned park property at 1200 North Cockrell Hill Road (up to $57.9M), amends the Dallas Memorial Auditorium agreement with Full Court Partners LLC dba Dallas Wings, and reduces the McKissack and McKissack project management contract by $1,847,485 to eliminate the Dallas Wings Practice Facility scope.

…enter Revenue Bonds Series 2023 Fund (-$1,847,485.00) *In alignment with the Kay Bailey Hutchison Convention Center Dallas Master Plan. jesse.saldana@dallascityhall.com

$56.0M
Items For Individual Consideration

Authorize Supplemental Agreement No. 2 to the CMAR contract with Trinity Alliance Ventures, LLC, accepting a Guaranteed Maximum Price of $695,680,181 for construction of the Kay Bailey Hutchison Convention Center Dallas expansion west of Lamar, with owner's contingency, bringing the total CMAR contract to $984,394,571.40 financed by CCT 2025 Senior Lien Special Tax Revenue Notes.

…ing: CCT 2025 Senior Lien Special Tax Revenue Notes Fund *In alignment with Kay Bailey Hutchison Convention Center Dallas Master Plan. jesse.saldana@dallascityhall.com

$717.5M
Briefing Items

Briefing on the Kay Bailey Hutchison Convention Center Dallas Master Plan and a related loan application to the TxDOT State Infrastructure Bank, presented by the Director of Tourism, Conventions, and Events.

Kay Bailey Hutchison Convention Center Dallas Master Plan - TxDOT State Infrastructure Bank Loan Application [Rosa Fleming, Director, Tourism, Conventions, and Events]

January 2026

Items For Individual Consideration

Authorizes an increase of $26 million to a previously approved State Infrastructure Bank loan application, raising the total loan amount to $116 million to finance transportation improvements and demolition surrounding the Kay Bailey Hutchison Convention Center.

…ion Center - Financing: No cost consideration to the City *In alignment with Kay Bailey Hutchison Convention Center Dallas Master Plan. NC jesse.saldana@dallascityhall.com

Briefing Items

A briefing on the Transportation Communication Plan developed as part of the Kay Bailey Hutchison Convention Center Dallas Master Plan, addressing transportation coordination and public outreach strategies.

Kay Bailey Hutchison Convention Center Dallas Master Plan - Transportation Communication Plan [Rosa Fleming, Director, Convention and Event Services; Gus Khankarli, Director, Transportation and Public

November 2025

Consent Agenda

Authorizes an Interlocal Agreement with Dallas Area Rapid Transit (DART) for activities during the first 18 months of the Kay Bailey Hutchison Convention Center redevelopment project, covering temporary closure and vacation of the on-site DART facility, at a cost not to exceed $3,000,000 from the Convention Center Capital Construction Fund.

Authorize an Interlocal Agreement (“ILA”) with Dallas Area Rapid Transit (hereinafter "DART") for activities occurring during the first eighteen months of the Project related to the temporary closure

$3.0M

September 2025

Briefing Memos

Briefing on Supplemental Agreement No. 2 with McKissack & McKissack, Inc. for project manager and owner's representative services supporting Kay Bailey Hutchison Convention Center Dallas Master Plan Component Three and the delivery of the Dallas Wings secondary facility at 1200 N. Cockrell Hill Road.

…. for services associated with (1) the implementation of Component Three of the Kay Bailey Hutchison Convention Center Dallas Master Plan; and (2) delivery of the secondary facility of the Dallas Wings located at 1200…

June 2025

Consent Agenda

Authorization for a Construction Manager at Risk Agreement with HJ Russell - Phillips May - STSW, A Joint Venture for pre-construction and construction services for Kay Bailey Hutchison Convention Center Dallas Master Plan Component Four, which includes renovation and reconstruction of The Black Academy of Arts and Letters, with a pre-construction fee not to exceed $695,363 and construction management at 3% of the cost of work within a $200 million total project construction budget.

…value proposer of three, for pre-construction and construction services for the Kay Bailey Hutchison Convention Center Dallas Master Plan Component Four for renovation and reconstruction of The Black Academy of Arts a…

$695K