Ordinance amending the existing “Project Financing Zone Number One, City of Corpus Christi, Texas” (the “Zone”) for the Hilliard Center Complex; making certain findings related thereto; directing that the Texas Comptroller of Public Accounts be notified of the amendments of the Zone; requesting that the Comptroller deposit incremental hotel-associated tax revenues from the amended Zone into a suspense account held in trust for the Qualified Project Activities; and containing other related matters.

site_specificCity Council
The City Council amended the Project Financing Zone Number One ordinance for the Hilliard Center Complex in Corpus Christi. Project Financing Zones allow cities to capture tax increment revenue to fund public improvements that support economic development. The amendment was approved unanimously on February 17, 2026.
2 eventsFirst seen Feb 10, 2026Last activity Feb 17, 2026File #: 25-1827
City Council: Carried: 9 to 0Feb 17, 2026
Topics
tax
development
governance

Get notified on new hearings, votes, or status changes for this matter.

Actions

Showing all 4 actions. Filter by: , , , .

Attorney
As of Feb 2026

Flag new pre-encroachment easement license ordinance

Context: Adopted on second reading by unanimous 9-0 vote on Feb 17, 2026.

Recommended: A new ordinance lets the city authorize easement encroachment licenses before the encroachment occurs, reversing the usual after-the-fact remediation sequence — advise clients with pending or planned encroachments to apply proactively under this process rather than seeking retroactive cure.

Source: City Council — Feb 17, 2026 →
Developer
As of Feb 2026

Apply for Hilliard Center hotel tax trust funding

Context: Amendment passed first reading 9-0 on Feb 10 and was adopted on second reading 9-0 on Feb 17.

Recommended: The amended financing ordinance now redirects incremental hotel-associated tax revenue at Hilliard Center Complex into a dedicated trust account for qualified project activities — if you have work in that zone, request the trust account administration procedures before assuming reimbursement isn't available.

Source: City Council — Feb 17, 2026 →
Journalist
As of Feb 2026

Identify the lone dissenting vote among 29 motions

Context: Meeting record notes 'all but one of 29 motions passed unanimously' while every tracked item here shows Carried 9-0.

Recommended: Every item on this agenda — including both readings of this ordinance and the two rezonings — carried 9-0, but one of the meeting's 29 motions did not pass unanimously; pull the full agenda minutes to find which item broke the pattern and why.

Source: City Council — Feb 17, 2026 →
Resident
As of Feb 2026

Expect new subdivision buildout along FM 2444

Context: Second-reading rezoning ordinance carried 9-0 on Feb 17, 2026.

Recommended: Council rezoned more than half of a 109-acre annexation along FM 2444 to single-family use for a new subdivision, so residents nearby should anticipate construction traffic and infrastructure work in the coming months.

Source: City Council — Feb 17, 2026 →

Key Entities

View relationship map

Loading relationship map…

Timeline

Vote
Carried: 9 to 0

Ordinance amending the existing “Project Financing Zone Number One, City of Corpus Christi, Texas” (the “Zone”) for the Hilliard Center Complex; making certain findings related thereto; directing that the Texas Comptroller of Public Accounts be notified of the amendments of the Zone; requesting that the Comptroller deposit incremental hotel-associated tax revenues from the amended Zone into a suspense account held in trust for the Qualified Project Activities; and containing other related matters.

Vote: 9 for, 0 against

pass on second reading; amend Project Financing Zone One for Hilliard Center Complex

Vote
Carried: 9 to 0

Ordinance amending the existing “Project Financing Zone Number One, City of Corpus Christi, Texas” (the “Zone”) for the Hilliard Center Complex; making certain findings related thereto; directing that the Texas Comptroller of Public Accounts be notified of the amendments of the Zone; requesting that the Comptroller deposit incremental hotel-associated tax revenues from the amended Zone into a suspense account held in trust for the Qualified Project Activities; and containing other related matters.

Vote: 9 for, 0 against

approve Project Financing Zone Number One amendment for Hilliard Center Complex on first reading