Case File 25-1983
View full legal title
Ordinance approving an amendment to the Tax Increment Reinvestment Zone No. 2 (“TIRZ #2”) Operating Budget by authorizing the transfer of $2,100,166.00, from CIP reserve to the TIRZ #2 Operating Fund for the Briscoe King Pavilion Project; increasing funds in the amount of $2,100,166.00, for needed improvements and renovation to the Briscoe King Pavilion Project; appropriating $2,100,166.00, from the unreserved fund balance of the Reinvestment Zone No. 2 Fund; and amending the FY 2026 operating budget adopted by Ordinance No. 033730 by increasing expenditures by $2,100,166.00, for payment to Nueces County for the Briscoe King Pavilion Project.
Get notified on new hearings, votes, or status changes for this matter.
Actions
Showing all 4 actions. Filter by: , , , .
Confirm tax-increment plan covers District 3/5 utility work
Context: Council approved $922,320 in reimbursement agreements with MPM Development, LP for Districts 3/5 utility work on consent agenda both Jan 13 and Jan 27, 9-0 each time, with no plan-eligibility discussion in the record.
Recommended: Pull the TIRZ #2 project and financing plan and check whether the transmission line and sewer extension reimbursements to MPM Development are listed as eligible improvements — reimbursements outside a zone's adopted plan are vulnerable to challenge under Texas Tax Code Chapter 311.
Check bid postings for the Briscoe King Pavilion Project
Context: Council appropriated $2.1 million in TIRZ #2 funds for the Briscoe King Pavilion Project on second reading, Item 13, carried 9-0 on Jan 27.
Recommended: Watch the City of Corpus Christi purchasing portal for a construction solicitation tied to the Briscoe King Pavilion Project now that its funding has cleared final council approval.
Seek tax-increment reimbursement for District 3/5 subdivision utilities
Context: Council approved reimbursement agreements with MPM Development, LP totaling $922,320 for transmission lines and a sewer extension serving new subdivisions in Districts 3 and 5, passed 9-0 on Jan 27.
Recommended: If you're building a residential subdivision in Council District 3 or 5, ask the city's Tax Increment Reinvestment Zone (TIRZ) #2 office whether your water/wastewater line costs qualify for a reimbursement agreement like the ones MPM Development just secured — don't assume you have to absorb the full infrastructure cost yourself.
Reconcile conflicting count of MPM's Districts 3/5 utility deals
Context: First-reading (Jan 13) and second-reading (Jan 27) accounts of the same 9-0 votes disagree on whether MPM Development got three or four reimbursement agreements.
Recommended: Request the signed Jan 27 ordinance and agreements from the city clerk — one summary of the vote says MPM Development received four reimbursement agreements, another says three, both citing the same $922,320 total, and neither reading drew any council discussion.
Key Entities
View relationship map
Loading relationship map…
Timeline
Ordinance approving an amendment to the Tax Increment Reinvestment Zone No. 2 (“TIRZ #2”) Operating Budget by authorizing the transfer of $2,100,166.00, from CIP reserve to the TIRZ #2 Operating Fund for the Briscoe King Pavilion Project; increasing funds in the amount of $2,100,166.00, for needed improvements and renovation to the Briscoe King Pavilion Project; appropriating $2,100,166.00, from the unreserved fund balance of the Reinvestment Zone No. 2 Fund; and amending the FY 2026 operating budget adopted by Ordinance No. 033730 by increasing expenditures by $2,100,166.00, for payment to Nueces County for the Briscoe King Pavilion Project.
Vote: 9 for, 0 against
approve amendment to TIRZ #2 Operating Budget for Briscoe King Pavilion Project
Ordinance approving an amendment to the Tax Increment Reinvestment Zone No. 2 (“TIRZ #2”) Operating Budget by authorizing the transfer of $2,100,166.00, from CIP reserve to the TIRZ #2 Operating Fund for the Briscoe King Pavilion Project; increasing funds in the amount of $2,100,166.00, for needed improvements and renovation to the Briscoe King Pavilion Project; appropriating $2,100,166.00, from the unreserved fund balance of the Reinvestment Zone No. 2 Fund; and amending the FY 2026 operating budget adopted by Ordinance No. 033730 by increasing expenditures by $2,100,166.00, for payment to Nueces County for the Briscoe King Pavilion Project.
Vote: 9 for, 0 against
approve ordinance amending TIRZ #2 Operating Budget, transferring $2,100,166 for Briscoe King Pavilion Project (first reading)