Case File 26-0113

View full legal title

Ordinance authorizing the City Manager, or designee, to execute a 5-year Reclaimed Water Supply Agreement and associated License for Use of Premises with Flint Hills Resources Corpus Christi, LLC, for the sale and delivery of up to 2 million gallons per day of reclaimed water from the Allison Wastewater Treatment Plant, and providing for related fees, responsibilities, and terms, with option to renew for additional 5-year term.

site_specificCity Council
The city authorized a 5-year agreement to purchase up to 2 million gallons per day of reclaimed water from the Allison Wastewater treatment facility, supplied by Flint Hills Resources Corpus Christi, LLC. This reclaimed water supply supports the city's water conservation and sustainability objectives by providing a reliable alternative water source. The ordinance was approved unanimously by City Council.
2 eventsFirst seen Jan 27, 2026Last activity Feb 10, 2026File #: 26-0113
City Council: Carried: 9 to 0Feb 10, 2026
Topics
utilities
contract
environment

Get notified on new hearings, votes, or status changes for this matter.

Actions

Showing all 4 actions. Filter by: , , , .

Attorney
As of Feb 2026

Confirm TIRZ board approval for Padre Island seawall funds

Context: The 2026-02-10 consent vote combined an $11.1M reallocation for the North Padre Island Seawall with a separate $2.1M TIRZ #2 transfer for the Briscoe King Pavilion Project.

Recommended: This batch moved $11.1 million into the North Padre Island Seawall project and $2.1 million into the Briscoe King Pavilion Project out of the same TIRZ #2 fund in one sitting — pull the TIRZ #2 board's own minutes to confirm the board ratified both reallocations before council acted, since zone-fund shifts of this size typically require board sign-off first.

Source: City Council — Feb 10, 2026 →
Developer
As of Feb 2026

Pull MPM reimbursement terms for District 3, 5 subdivisions

Context: Four MPM Development, LP reimbursement agreements for Districts 3 and 5 subdivisions passed on the same 9-0 consent vote as this ordinance on 2026-02-10.

Recommended: Four infrastructure reimbursement agreements with MPM Development, LP for subdivisions in Districts 3 and 5 rode through on this same consent vote — request copies to see the city's current reimbursement rate and eligible cost categories, since that's the deal structure council just approved for comparable subdivision work.

Source: City Council — Feb 10, 2026 →
Journalist
As of Feb 2026

Ask why $63.7M seawall, marina package skipped debate

Context: The 2026-02-10 meeting bundled $63.7M in financial commitments — a $6.6M marina contract with B.E. Beecroft, a $1.4M drainage contract with Mako Contracting, and an $11.1M seawall reallocation — into one 9-0 consent vote among 45 substantive items.

Recommended: Request the individual staff memos for the $6.6M marina contract, $1.4M drainage contract, and $11.1M seawall reallocation — all three moved as part of a 45-item consent block with zero floor discussion, so the staff record is the only place left to check whether council reviewed engineering or bid specifics before voting.

Source: City Council — Feb 10, 2026 →
Resident
As of Feb 2026

Watch for Padre Island seawall construction start

Context: The $11.1 million TIRZ #2 reallocation was approved on the 2026-02-10 consent vote specifically to 'fully fund' the North Padre Island Seawall CIP Project.

Recommended: Council fully funded the North Padre Island Seawall with an $11.1 million reallocation in this same batch, so expect crews to mobilize now rather than the project sitting on a funding wait list — check for permit postings if you're near the seawall corridor.

Source: City Council — Feb 10, 2026 →

Timeline

Vote
Carried: 9 to 0

Ordinance authorizing the City Manager, or designee, to execute a 5-year Reclaimed Water Supply Agreement and associated License for Use of Premises with Flint Hills Resources Corpus Christi, LLC, for the sale and delivery of up to 2 million gallons per day of reclaimed water from the Allison Wastewater Treatment Plant, and providing for related fees, responsibilities, and terms, with option to renew for additional 5-year term.

Vote: 9 for, 0 against

approve 5-year Reclaimed Water Supply Agreement with Flint Hills Resources on second reading

Vote
Carried: 9 to 0

Ordinance authorizing the City Manager, or designee, to execute a 5-year Reclaimed Water Supply Agreement and associated License for Use of Premises with Flint Hills Resources Corpus Christi, LLC, for the sale and delivery of up to 2 million gallons per day of reclaimed water from the Allison Wastewater Treatment Plant, and providing for related fees, responsibilities, and terms, with option to renew for additional 5-year term.

Vote: 9 for, 0 against

approve 5-year Reclaimed Water Supply Agreement