The Municipal Court Department proposes amendments to Chapter 10 of the City Code and a revised parking-fine schedule. The changes would modernize court administration, judicial appointments and reporting, court security, parking adjudication, and statutory references.
…ordination with the City Attorney’s Office, the Chief Judge, and staff from the Transportation and Public Works Department, conducted a comprehensive review of Chapter 10, Articles I and II o…
June 2026
Authorizes an Interlocal Agreement with Tarrant County Precinct 4 for full-depth reclamation and asphalt overlay of Silver Creek Road from Heron Drive to the City limits and North Las Vegas Trail from North Jim Wright Freeway to Heron Drive, covering approximately 3.03 lane miles. Tarrant County provides labor and equipment while the City pays $1,172,700.00 for materials and incidentals plus traffic control.
…by April 2027. Funding is budgeted in the General Capital Projects Fund for the Transportation and Public Works Department for the purpose of funding the 2026 Interlocal Agreement with Tarran…
Authorizes Amendment No. 1 in an amount up to $163,695.00 to City Secretary Contract No. 56946, a Professional Services Agreement with Walter P. Moore and Associates, Inc., for a revised contract amount up to $363,695.00 to complete the FEMA Letter of Map Revision floodplain mapping updates project. The added capacity covers scope changes from FEMA review comments and additional work requested by the City's Floodplain Administrator.
…$363,695.00 Funding is budgeted in the Stormwater Capital Projects Fund for the Transportation and Public Works Department for the purpose of funding the FEMA LOMR Updates-SWS-091 project, as…
Authorizes two public highway at-grade crossing improvement agreements with Fort Worth & Western Railroad Company for railroad sidewalk crossing improvements at East Berry Street ($250,000.00) and East Seminary Drive ($200,000.00), adopts an appropriation ordinance moving $450,000.00 within the 2022 Bond Program Fund from the Sidewalks programmable project to the East Berry St & East Seminary Dr Sidewalk project, and amends the FY2026-2030 Capital Improvement Program.
…e construction of a 6-foot-wide sidewalk at the project locations identified by Transportation and Public Works (TPW), Transportation Management Division. E Berry & E Seminary FWWRR project (…
Authorizes Amendment No. 1 in the amount of $49,880.00 to City Secretary Contract No. 61583, a professional services agreement with Halff Associates, Inc., for a revised contract total of $149,530.00 to complete the National Flood Insurance Program Repetitive Loss Area Analysis Update 2024, including additional work for newly identified repetitive loss areas.
…ion of the amendment to the agreement. Prior to any expense being incurred, the Transportation and Public Works Department has the responsibility to validate the availability of funds. SUBMIT…
City Council is asked to rescind Resolution No. 6229-01-2026, repeal Appropriation Ordinance No. 28214-01-2026, adopt a new resolution authorizing a $1,437,777.00 Advance Funding Agreement with TxDOT (with $154,468.00 local participation) for intersection improvements at Business 287 (Mansfield Highway) and Wichita Street, adopt an appropriation ordinance for up to $216,986.00 in the Grants Capital Project State Fund, and amend the FY2026-2030 Capital Improvement Program.
…hway) at Wichita Street Date: 06/23/26 M&C File Number: M&C 26-0515 Department: Transportation Public Works Subject (CD 8 and CD 11) Rescind Resolution Number 6229-01-2026, R…
City Council is asked to adopt a resolution authorizing Amendment No. 2 to the Advance Funding Agreement with TxDOT for the Oakland Boulevard and Miller Avenue Safe Streets project (2022 Bond Program), reducing the AFA total from $3,150,837.00 to $3,007,579.00 with City participation of $999,709.00 plus cost overruns.
…and Blvd. & Miller Ave. Date: 06/23/26 M&C File Number: M&C 26-0514 Department: Transportation Public Works Subject (CD 5, CD 8, and CD 11) Adopt Resolution Authorizing Execu…
City Council is asked to rescind Resolution No. 6230-01-2026 and adopt a revised resolution authorizing an Advance Funding Agreement with TxDOT for intersection improvements at Business 287 (North Main Street) and 29th Street, reflecting updated cost allocations. The AFA totals $1,014,970.00 with federal, state, and local participation shares.
…Street) at 29th Street Date: 06/23/26 M&C File Number: M&C 26-0513 Department: Transportation Public Works Subject (CD 2) Rescind Resolution Number 6230-01-2026, Adopt Resol…
Adopt a resolution authorizing an Advance Funding Agreement with TxDOT totaling $6,217,108 (with $6,200,027 in federal participation) for the Fort Worth Traffic Signal Equipment Standardization project upgrading detection and communication equipment at approximately 300 signalized intersections, and adopt the related appropriation ordinance.
…uipment Standardization Date: 06/23/26 M&C File Number: M&C 26-0524 Department: Transportation Public Works Subject (ALL) Adopt Resolution Authorizing Execution of an Advance…
Authorizes Change Order No. 4 to the construction contract with William J. Schultz, Inc. dba Circle C Construction Company for the Westcliff Drainage Improvements Phase 1 and Sanitary Sewer Rehabilitation Contract 91 Part 2, decreasing the contract by $210,006.05 and adding 308 calendar days for a revised contract amount of $17,791,709.90.
…needed for this change order. The construction cost will be shared between the Transportation and Public Works Department Stormwater Division and the Water Department. The Stormwater constru…