· City Council Meeting
Oakland Boulevard and Miller Avenue Safe Streets Engineering Contract Amendment #2
- Money
$3.4M in total financial activity across agenda items that mention this location.
Largest single item: $3.0M on (AFA Amendment #2 with TxDOT for Oakland Blvd. & Miller Ave.)
Mention Frequency
Topic Distribution
Topics
Roles
Related Entities
View network map
Loading network map…
Activity Timeline
September 2026
Authorizes Amendment No. 2 in the amount of $111,288.20 to an engineering services agreement with Dunaway Associates, LLC for the Oakland Boulevard and Miller Avenue Safe Streets project, for a revised contract amount of $649,224.00, and adopts appropriation ordinances reallocating 2018 and 2022 Bond Program funds while amending the FY2026-2030 Capital Improvement Program.
Oakland Boulevard and Miller Avenue Safe Streets Engineering Contract Amendment #2
August 2026
Site plan amendment SP-26-008 for 'PD311' Planned Development at 4213 Miller Avenue (0.89 acres) to add a new enclosed auto repair facility within the Stop Six Residential Overlay. Staff and the Zoning Commission (9-0) recommend approval.
SP-26-008 (CD 11) (Address 4213 Miller Avenue)
June 2026
Authorizes Amendment No. 1 in an amount up to $163,695.00 to City Secretary Contract No. 56946, a Professional Services Agreement with Walter P. Moore and Associates, Inc., for a revised contract amount up to $363,695.00 to complete the FEMA Letter of Map Revision floodplain mapping updates project. The added capacity covers scope changes from FEMA review comments and additional work requested by the City's Floodplain Administrator.
…SC-7 Watershed in Council Districts 6 and 8; and Eastland Creek from generally Miller Avenue downstream to Lake Arlington in Council Districts 5 and 11. Additional contract…
City Council is asked to adopt a resolution authorizing Amendment No. 2 to the Advance Funding Agreement with TxDOT for the Oakland Boulevard and Miller Avenue Safe Streets project (2022 Bond Program), reducing the AFA total from $3,150,837.00 to $3,007,579.00 with City participation of $999,709.00 plus cost overruns.
AFA Amendment #2 with TxDOT for Oakland Blvd. & Miller Ave.
Site plan amendment SP-26-008 for 0.89 acres at 4213 Miller Avenue in 'PD311' Planned Development to add a new enclosed auto repair facility with a revised site layout, reducing bay doors from seven to five, within the Stop Six Residential Overlay. Staff and Zoning Commission recommended approval (9-0).
SP-26-008 (CD 11) (Address 4213 Miller Avenue)