Municue

Oakland Boulevard

location
3 mentions across 2 events
Based on city records: Entity referenced in Fort Worth city proceedings. Appears in topics: contract, budget, transportation, bond, utilities.
2 eventsLast active Tracked since $3.0M city spendingUpdated September 2026

Key facts

Money

$3.0M in total financial activity across agenda items that mention this location.

Largest single item: $3.0M on (AFA Amendment #2 with TxDOT for Oakland Blvd. & Miller Ave.)

Mention Frequency

Topic Distribution

Topics

bond (2)
transportation (2)
budget (2)
contract (2)
public safety (2)
governance (1)
utilities (1)
development (1)

Roles

mentioned (3)
View network map

Loading network map…

Activity Timeline

September 2026

General - Consent Items

Authorizes Amendment No. 2 in the amount of $111,288.20 to an engineering services agreement with Dunaway Associates, LLC for the Oakland Boulevard and Miller Avenue Safe Streets project, for a revised contract amount of $649,224.00, and adopts appropriation ordinances reallocating 2018 and 2022 Bond Program funds while amending the FY2026-2030 Capital Improvement Program.

Oakland Boulevard and Miller Avenue Safe Streets Engineering Contract Amendment #2

General - Consent Items

Authorizes a $4,980,914.30 construction contract with Woody Contractors, Inc. for the Sanitary Sewer Rehabilitation Contract 116 project, replacing cast iron water and deteriorated sanitary sewer mains on streets in Council Districts 8, 9, and 11, and adopts an appropriation ordinance of $5,660,817.00 from Water and Sewer PayGo funds.

…e Road and Sahara Place 260 feet North of Broadus Avenue North 305 feet Sewer 8 Oakland Boulevard 200 feet North of Lancaster Avenue North 900 feet Sewer 11 Easement South of Br…

June 2026

General - Consent Items

City Council is asked to adopt a resolution authorizing Amendment No. 2 to the Advance Funding Agreement with TxDOT for the Oakland Boulevard and Miller Avenue Safe Streets project (2022 Bond Program), reducing the AFA total from $3,150,837.00 to $3,007,579.00 with City participation of $999,709.00 plus cost overruns.

AFA Amendment #2 with TxDOT for Oakland Blvd. & Miller Ave.

$3.0M