Municue

Mary’s Creek

location
2 mentions across 2 events
2 eventsLast active Tracked since

Key facts

Latest action

· City Council Meeting

Jackson Construction, Ltd Change Order No. 2 for Sewer Contract 127

Result: Approved. Appropriation Ordinance 26-28696.

Topic Distribution

Topics

utilities (2)
contract (2)
development (1)
budget (1)
permit (1)
environment (1)

Roles

mentioned (2)
View network map

Loading network map…

Activity Timeline

August 2026

Award Of Contract - Consent Items

Authorizes Change Order No. 2 in the amount of $206,308.40 to the contract with Jackson Construction, Ltd. for the Sanitary Sewer Contract 127 project, raising the contract to $2,619,428.40, and adopts an appropriation ordinance increasing the Water and Sewer Capital Projects Fund by $206,309.00 from PayGo funds.

…that was necessary due to unsuitable subgrade material that was encountered on Mary’s Creek Drive. Change Order No. 2 primarily provides for increased pay item quantities…

Informal Reports

The report briefs Council on procurement and the anticipated construction schedule for the Mary’s Creek Water Reclamation Facility, which will initially treat 10 MGD of wastewater and may expand to 15 MGD. The facility will support west-side wastewater service and reclaimed-water delivery.

…nformal Report is to brief the City Council on the background and status of the Mary’s Creek Water Reclamation Facility contractor procurement process and anticipated const…