Authorize Change Order No. 2 with Jackson Construction, Ltd. for Sanitary Sewer Contract 127 and appropriate Water and Sewer funds for the project. The change order addresses additional construction needs identified during sewer work.
…that was necessary due to unsuitable subgrade material that was encountered on Mary’s Creek Drive. Change Order No. 2 primarily provides for increased pay item quantities…
The report briefs Council on procurement and the anticipated construction schedule for the Mary’s Creek Water Reclamation Facility, which will initially treat 10 MGD of wastewater and may expand to 15 MGD. The facility will support west-side wastewater service and reclaimed-water delivery.
…nformal Report is to brief the City Council on the background and status of the Mary’s Creek Water Reclamation Facility contractor procurement process and anticipated const…