Municue

Sanitary Sewer Contract 127 Project

project
2 mentions across 2 events
2 eventsLast active Tracked since $263K city spending

Mention Frequency

Topic Distribution

Topics

utilities (2)
contract (2)
development (1)
budget (1)

Roles

mentioned (2)
View network map

Loading network map…

Activity Timeline

August 2026

Award Of Contract - Consent Items

Authorizes Change Order No. 2 in the amount of $206,308.40 to the contract with Jackson Construction, Ltd. for the Sanitary Sewer Contract 127 project, raising the contract to $2,619,428.40, and adopts an appropriation ordinance increasing the Water and Sewer Capital Projects Fund by $206,309.00 from PayGo funds.

…in the Amount of $206,308.40 to a Contract with Jackson Construction, Ltd., for Sanitary Sewer Contract 127 Project and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution t…

January 2026

Award Of Contract Consent

Authorizes Change Order No. 1 adding $262,860.00 to an existing contract with Jackson Construction, Ltd. for the Sanitary Sewer Contract 127 Project, and adopts an appropriation ordinance to fund the Water department's contribution to the FY2026–2030 Capital Improvement Program.

(CD 3 and City of Benbrook) Authorize Execution of Change Order No. 1 in the Amount of $262,860.00 to a Contract with Jackson Construction, Ltd., for Sanitary Sewer Contract 127 Project and Adopt Appr

$263K