March 2026
Authorizes Change Order No. 1 increasing a construction contract with Jackson Construction, Ltd. by $1,159,312.05 for the Water & Sanitary Sewer Replacement Contract 2020, WSM-K Project, and adopts an appropriation ordinance to fund Water's contribution to the FY2026-2030 Capital Improvement Program.
(CD 3) Authorize Execution of Change Order No. 1 in the Amount of $1,159,312.05 to a Contract with Jackson Construction, Ltd., for the Water & Sanitary Sewer Replacement Contract 2020, WSM-K Project a
January 2026
Authorizes Change Order No. 1 adding $262,860.00 to an existing contract with Jackson Construction, Ltd. for the Sanitary Sewer Contract 127 Project, and adopts an appropriation ordinance to fund the Water department's contribution to the FY2026–2030 Capital Improvement Program.
(CD 3 and City of Benbrook) Authorize Execution of Change Order No. 1 in the Amount of $262,860.00 to a Contract with Jackson Construction, Ltd., for Sanitary Sewer Contract 127 Project and Adopt Appr