Award Of Contract Consent

The city authorizes Change Order No. 3, increasing the construction contract with Circle C Construction Company by $1,498,305.57 to a revised total of $11,003,227.57 for the Central City New Main Street Outfall Storm Drain & 8th Street Project, with associated appropriation ordinances and an amendment to the FY2026–2030 Capital Improvement Program.

…eement with William J. Schultz, Inc. dba Circle C Construction Company, for the Fort Worth Central City New Main Street Outfall Storm Drain & 8th Street Project, for a Revised Contract Amount of $11,003,227.57, Adopt Appropriation Ordinance…