Fort Worth Central City New Main Street Outfall Storm Drain & 8th Street Project
project
1 mention across 1 event
1 eventLast active Tracked since $1.5M city spending
Topic Distribution
Topics
utilities (1)
contract (1)
budget (1)
Roles
mentioned (1)
View network map
Loading network map…
Activity Timeline
January 2026
Award Of Contract Consent
The city authorizes Change Order No. 3, increasing the construction contract with Circle C Construction Company by $1,498,305.57 to a revised total of $11,003,227.57 for the Central City New Main Street Outfall Storm Drain & 8th Street Project, with associated appropriation ordinances and an amendment to the FY2026–2030 Capital Improvement Program.
…eement with William J. Schultz, Inc. dba Circle C Construction Company, for the Fort Worth Central City New Main Street Outfall Storm Drain & 8th Street Project, for a Revised Contract Amount of $11,003,227.57, Adopt Appropriation Ordinance…
$1.5M