Sanitary Sewer Rehabilitation Contract 91

project
1 mention across 1 event
1 eventLast active Tracked since $17.8M city spending

Topic Distribution

Topics

utilities (1)
contract (1)
environment (1)
transportation (1)

Roles

mentioned (1)
View network map

Loading network map…

Activity Timeline

June 2026

General - Consent Items

Authorizes Change Order No. 4 to the construction contract for Westcliff Drainage Improvements, Phase 1 and Sanitary Sewer Rehabilitation Contract 91, Part 2. The change order reduces the contract by $210,006.05, adds 308 calendar days, and revises the contract total to $17,791,709.90.

…le C Construction Company for the Westcliff Drainage Improvements, Phase 1, and Sanitary Sewer Rehabilitation Contract 91, Project Part 2 Recommendation It is recommended that the City Council authoriz…

$17.8M