Lee Lewis Construction, Inc.
organization
1 mention across 1 event
1 eventLast active Tracked since $13.6M city spending
Topic Distribution
Topics
parks (1)
contract (1)
budget (1)
Roles
vendor (1)
Related Entities
View network map
Loading network map…
Activity Timeline
July 2026
Cc - Approval Of Change Order
vendor
Approval of Change Order No. 1 decreasing the construction contract with Lee Lewis Construction, Inc. for the Tom Muehlenbeck Recreation Center renovation (Project No. FAC-F-7525) by $131,544.25, reducing the total contract to $13,436,658.75.
…- Tom Muehlenbeck Recreation Center - Renovation, Project No. FAC-F-7525, from Lee Lewis Construction, Inc. for the Engineering - Facilities Division; and authorizing the City Manager to…