Pecan Hollow Golf Course Erosion Control for Holes 6 and 7

project
2 mentions across 2 events
2 eventsLast active Tracked since $6.7M city spending

Mention Frequency

Topic Distribution

Topics

parks (2)
contract (2)
environment (2)

Roles

mentioned (2)

Connected Matters

Legislative threads where Pecan Hollow Golf Course Erosion Control for Holes 6 and 7 is mentioned

Pecan Hollow Golf Course Erosion Control Contract Increase (26-582)

2 hearings since May 2026·Last: Jul 1, 2026·Contract·Site

Location

View network map

Loading network map…

Activity Timeline

July 2026

Cc - Approval Of Change Order

Approval of a $711,337 increase (Change Order No. 1) to the contract with Cardinal Strategies Construction Services, LLC for erosion control work on Holes 6 and 7 at Pecan Hollow Golf Course, bringing the total contract amount to $4,058,971.

To approve an increase to the current awarded contract amount of $3,347,634 by $711,337 for a total contract amount of $4,058,971 for Pecan Hollow Golf Course Erosion Control for Holes 6 and 7, Projec

$3.3M

May 2026

Cc - Approval Of Change Order

This item approves a change order increasing the contract for erosion control work at Pecan Hollow Golf Course (Holes 6 and 7) by $711,337, raising the total contract amount from $3,347,634 to $4,058,971, awarded to Cardinal Strategies Construction Services, LLC for the Engineering Department.

To approve an increase to the current awarded contract amount of $3,347,634 by $711,337 for a total contract amount of $4,058,971 for Pecan Hollow Golf Course Erosion Control for Holes 6 and 7, Projec

$3.3M