Pecan Hollow Golf Course Erosion Control Contract Increase (26-582)

2 hearings since May 2026·Last: Jul 1, 2026·Contract·Site

Location

View network map

Loading network map…

Activity Timeline

July 2026

Cc - Approval Of Change Order

Approval of a $711,337 increase (Change Order No. 1) to the contract with Cardinal Strategies Construction Services, LLC for erosion control work on Holes 6 and 7 at Pecan Hollow Golf Course, bringing the total contract amount to $4,058,971.

…t No. ENG-D-7419.1, from Cardinal Strategies Construction Services, LLC for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract…

$3.3M

May 2026

Cc - Approval Of Change Order

This item approves a change order increasing the contract for erosion control work at Pecan Hollow Golf Course (Holes 6 and 7) by $711,337, raising the total contract amount from $3,347,634 to $4,058,971, awarded to Cardinal Strategies Construction Services, LLC for the Engineering Department.

…t No. ENG-D-7419.1, from Cardinal Strategies Construction Services, LLC for the Engineering Department; and authorizing the City Manager to execute all necessary documents. (Contract…

$3.3M