Municue

Stephanie Pearson

person
12 mentions across 5 events
Based on city records: Individual who has appeared as requester in Plano city proceedings. Appears in topics: contract, utilities, transportation, development, environment.
5 eventsLast active Tracked since $10.7M city spendingUpdated October 2026

Key facts

Mention Frequency

Topic Distribution

Topics

contract (12)
utilities (8)
development (7)
transportation (6)
environment (3)
parks (1)

Roles

mentioned (7)
requester (5)
View network map

Loading network map…

Activity Timeline

October 2026

Cc - Award/Rejection Of Bid/Proposal

Award of RFB No. 2026-0572-B to North Rock Construction & Associates LLC for the Bob Woodruff South Sidewalk Connection project for the Parks and Recreation Department, with the City Manager authorized to execute documents.

…$311,139; and authorizing the City Manager to execute all necessary documents. Stephanie Pearson

$311K

September 2026

Cc - Approval Of Expenditure

Approval of an expenditure for engineering professional services from Walter P. Moore and Associates, Inc. for Erosion Control Improvements at various locations, and authorization for the City Manager to execute documents.

…partment; and authorizing the City Manager to execute all necessary documents. Stephanie Pearson

$270K

August 2026

Cc - Approval Of Change Order

Change Order No. 1 increasing the Tri-Con Services, Inc. contract for paving and water improvements on Monarch Drive, Charter Oak Drive, Kings Way, Queens Way, White Oak Drive and Desert Garden Drive by $136,286, for a new total of $4,080,437.

…xecute all necessary documents. (Contract No. 2025-0476-B; Change Order No. 1) Stephanie Pearson

$4.1M
Cc - Approval Of Expenditure

Approval of an expenditure of $339,250 for engineering professional services from Kimley-Horn and Associates, Inc. for the Jupiter Road Elevated Storage Tank Rehabilitation.

…partment; and authorizing the City Manager to execute all necessary documents. Stephanie Pearson

$339K
Cc - Approval Of Change Order
requester

Change Order No. 1 increasing the Tri-Con Services, Inc. contract for paving and water improvements on Monarch Drive, Charter Oak Drive, Kings Way, Queens Way, White Oak Drive and Desert Garden Drive by $136,286, for a new total of $4,080,437.

…xecute all necessary documents. (Contract No. 2025-0476-B; Change Order No. 1) Stephanie Pearson

$4.1M
Cc - Approval Of Change Order
requester

Approval of Change Order No. 7 increasing the contract with A & C Construction, Inc. by $405,916 (from $1,808,461 to $2,214,377) for the Plano Parkway sidewalk improvements project between Independence Parkway and Alma Drive for the Engineering Department.

…xecute all necessary documents. (Contract No. 2021-0213-B; Change Order No. 7) Stephanie Pearson

July 2026

Cc - Approval Of Expenditure
requester

Approval of a $206,000 expenditure with Huitt-Zollars, Inc. for engineering professional services for the Los Rios Boulevard Embankment Improvement project (Project No. ENG-S-00028) for the Engineering Department.

…partment; and authorizing the City Manager to execute all necessary documents. Stephanie Pearson

$206K
Cc - Approval Of Expenditure
requester

Approval of a $226,996 expenditure with HDR Engineering, Inc. for engineering professional services on the Aerial Crossings Erosion Control project covering Russell Creek, White Rock Creek and Young's Branch (Project No. ENG-SS-00009) for the Engineering Department.

…partment; and authorizing the City Manager to execute all necessary documents. Stephanie Pearson

$227K
Cc - Approval Of Expenditure
requester

Approval of an expenditure of $317,605 to LJB, Inc. for engineering professional services on the Water Rehabilitation - Old Shepard Place Phase 2 project (ENG-W-00007) for the Engineering Department.

…partment; and authorizing the City Manager to execute all necessary documents. Stephanie Pearson

$318K
Cc - Approval Of Expenditure

Approval of an expenditure of $386,507 to Raymond L. Goodson Jr., Inc. dba RLG Consulting Engineers for engineering professional services on the Water Rehabilitation - River Bend Phase 2 project (ENG-W-00006) for the Engineering Department.

…partment; and authorizing the City Manager to execute all necessary documents. Stephanie Pearson

$387K