May 2026

Consent Agenda

Authorization of Supplemental Agreement No. 1 to increase an engineering services contract with Criado & Associates, LLC by $652,711 for Phase II PS&E design of intersection improvements at Dallas Parkway/Frankford Road and Gaston Avenue/Tucker Street, funded through ARPA, General Fund, and GO Bond funds.

…Phase II) of intersection improvements at Dallas Parkway and Frankford Road and Gaston Avenue and Tucker Street to increase the contract by $652,711.00 from $326,039.00 to $978,750.00 - Not t…