June 2026
Authorizes a one-year renewal of job order construction contracting services with six vendors at the Kay Bailey Hutchison Convention Center, Eddie Bernice Johnson Union Station, Reunion Parking Garage, and other city facilities, increasing the contract ceiling by $1.75 million to a new total of $8.75 million.
Authorize Supplemental Agreement No. 1 to exercise the first of three, 1-year renewal options to the construction services contract with Brown & Root Industrial Services, LLC, Phoenix I Restoration &
May 2026
Authorizes the first one-year renewal option (Supplemental Agreement No. 1) to a job order contracting services contract for the Kay Bailey Hutchison Convention Center, Eddie Bernice Johnson Union Station, Reunion Parking Garage, and other city facilities with seven vendors, increasing the contract by $1,750,000 to a new total of $8,750,000.
Authorize Supplemental Agreement No. 1 to the construction services contract, for the first of three, one- year renewal options to perform job order contracting services at the Kay Bailey Hutchison Co
April 2026
Authorizes Supplemental Agreement No. 2 with Criado & Associates, LLC for professional engineering, subsurface utilities engineering, and survey services in alignment with the Kay Bailey Hutchison Convention Center Plan, increasing the contract by $1,000,000 from $2,642,569 to $3,642,569.
…nter Construction Fund (subject to annual appropriations) *In alignment with Kay Bailey Hutchison Convention Center Plan. bm.thompson@dallascityhall.com