Municue

Women's Museum Restoration Work (25-1892A)

View full legal title

Authorize a work order under the existing Job Order Contract, previously approved on November 13, 2024, by Resolution No. 24-1627, for construction services with Phoenix I Restoration and Construction, LLC. at The Women’s Museum located at 3800 Parry Avenue, Dallas, Texas 75210 for work associated with the temporary relocation of The Black Academy of Arts and Letters to facilitate construction and renovation of Component 4 of the Kay Bailey Hutchison Convention Center Master Plan - Not to exceed $5,913,458.00 - Financing - Convention Center Construction Fund

ContractcorridorCity Council
The matter concerns a work order for construction services by Phoenix I Restoration and Construction at The Women's Museum, 3800 Parry Avenue. The work falls under an existing Job Order Contract for facility improvements at a key cultural institution. This project supports maintenance and restoration efforts serving the Dallas community.
1 eventFirst seen Jun 11, 2025Last activity Jun 11, 2025File #: 25-1892A
City Council: Approved As An Individual ItemJun 11, 2025
Topics
contract
development
3800 Parry Avenue·Show on Google Maps ↗

Get notified on new hearings, votes, or status changes for this matter.

Actions

Showing all 2 actions. Filter by: , .

Contractor
As of Jun 2025

Confirm mobilization obligations under the approved Dallas corridor work order

Applies if: you are the contractor or subcontractor holding this Job Order Contract work order

Context: City Council adopted this work order on June 11, 2025 as the contracting authority, starting the contractual performance clock and activating any conditions precedent in the underlying Job Order Contract terms.

Recommended: If you hold this Job Order Contract work order, verify mobilization timelines, required documentation submissions, and any bonding or insurance thresholds triggered by the council authorization — the June 11, 2025 vote is the final approval to proceed.

Source: City Council — Jun 11, 2025 →
Journalist
As of Jun 2025

Request Dallas corridor work order records approved outside consent agenda

Context: The June 11, 2025 meeting had four items pulled from consent for individual votes, and this matter's timeline confirms it was 'Approved As An Individual Item' — but no public record of the discussion or dissent is surfaced in available data.

Recommended: Request the work order documents, contractor name, project scope, and dollar value from the Dallas City Secretary's office. This item was logged as approved 'as an individual item' rather than on the consent agenda, which can signal that at least one council member wanted discussion before the vote.

Source: City Council — Jun 11, 2025 →

Timeline

Vote
Approved As An Individual Item

Authorize a work order under the existing Job Order Contract, previously approved on November 13, 2024, by Resolution No. 24-1627, for construction services with Phoenix I Restoration and Construction, LLC. at The Women’s Museum located at 3800 Parry Avenue, Dallas, Texas 75210 for work associated with the temporary relocation of The Black Academy of Arts and Letters to facilitate construction and renovation of Component 4 of the Kay Bailey Hutchison Convention Center Master Plan - Not to exceed $5,913,458.00 - Financing - Convention Center Construction Fund