Rolling Hills Water Treatment Plant
Also known as: RHWTP
Mention Frequency
Topic Distribution
Topics
Roles
Related Entities
Location
View network map
Loading network map…
Activity Timeline
September 2026
Ratifies two emergency contracts totaling $920,324.30 with Circle C Construction ($588,424.30) and Acme Electric ($331,900.00) for emergency repairs to the 84-inch raw water line at the Rolling Hills Water Treatment Plant, and adopts an appropriation ordinance funding the work from Water and Sewer PayGo funds as part of the FY2026-2030 Capital Improvement Program.
Emergency Contracts for 84-inch Raw Water Line Repairs at Rolling Hills Water Treatment Plant
Authorizes a professional services agreement with Gresham Smith in an amount up to $425,000.00 for requirements assessment and preliminary design of Phase 1 of the Central Laboratory Expansion at Rolling Hills Water Treatment Plant. Also adopts an appropriation ordinance increasing the Water & Sewer Capital Projects Fund by $455,000.00 from PayGo funds for the project (City Project No. 106543).
Gresham Smith Professional Services Agreement for Central Laboratory Expansion at Rolling Hills Water Treatment Plant
March 2026
Adopts a $1,536,100 appropriation ordinance to fund the installation of switchgear and electrical feeder infrastructure at the Eagle Mountain and Rolling Hills Water Treatment Plants as part of the FY2026–2030 Capital Improvement Program.
(ALL) Adopt Appropriation Ordinance in the Amount of $1,536,100.00 to Fund the Installation of Switchgear and Electrical Feeder in Eagle Mountain and Rolling Hills Water Treatment Plants and to Effect