September 2026

General - Consent Items

Authorize Change Order No. 1 in the amount of $1,436,665.00 and 90 additional calendar days to the contract with William J. Schultz, Inc. dba Circle C Construction Company for the Large Diameter Pipe Bursting Contract ICAP Project Part 2 (M-468), revising the contract to $8,106,315.00, and adopt an appropriation ordinance increasing the Water & Sewer Capital Projects Fund by the same amount from PayGo funds.

Circle C Construction Company Contract for Large Diameter Pipe Bursting