Large Diameter Pipe Bursting Contract ICAP Project Part 2 (M-468)
project
1 mention across 1 event
1 eventLast active Tracked since $8.1M city spending
Topic Distribution
Topics
utilities (1)
contract (1)
development (1)
budget (1)
Roles
mentioned (1)
Related Entities
View network map
Loading network map…
Activity Timeline
September 2026
General - Consent Items
Authorize Change Order No. 1 in the amount of $1,436,665.00 and 90 additional calendar days to the contract with William J. Schultz, Inc. dba Circle C Construction Company for the Large Diameter Pipe Bursting Contract ICAP Project Part 2 (M-468), revising the contract to $8,106,315.00, and adopt an appropriation ordinance increasing the Water & Sewer Capital Projects Fund by the same amount from PayGo funds.
Circle C Construction Company Contract for Large Diameter Pipe Bursting
$8.1M