June 2026
Authorizes a professional engineering services contract with Westwood Professional Services, Inc. to conduct a traffic corridor study along North Beckley Avenue, Second Avenue, and Gaston Avenue, not to exceed $525,000 from the General Fund.
Authorize a professional engineering services contract for a traffic corridor study along the following: North Beckley Avenue from Singleton Boulevard to West 12th Street, Second Avenue from Fitzhugh
April 2026
Resolution directing the City Manager to use up to $200,000 in contingency reserve funds to hire a consultant to calculate a fee amount under Dallas City Code Section 51A-4.704 for properties at 2600 Singleton Boulevard and 7910 South Central Expressway, then schedule a council vote on depositing the calculated amount into the code-established fund.
…der Dallas City Code Section 51A-4.704(a)(1)(D)(i) for the uses located at 2600 Singleton Boulevard and 7910 South Central Expressway; (2) not later than 30 days after the consult…
Authorization of a cost-overrun payment to Union Pacific Railroad Company for additional costs incurred upgrading the Chalk Hill Road at-grade crossing between IH-30 frontage road and Singleton Boulevard, increasing the total contract from $1,308,399 to $2,008,399, funded by 2024B Certificates of Obligation.
…e public road crossing, between Interstate Highway-30 (IH-30) frontage road and Singleton Boulevard for the Public Highway At-grade Crossing Improvement Agreement with UPRR - Not…
A resolution directing the city manager to use contingency reserve funds to hire a consultant to calculate required fee amounts under Dallas City Code Section 51A-4.704 for properties at 2600 Singleton Boulevard and 7910 South Central Expressway, and to brief council and schedule a vote on depositing the determined amount into the statutory fund within 30 days.
…der Dallas City Code Section 51A-4.704(a)(1)(D)(i) for the uses located at 2600 Singleton Boulevard and 7910 South Central Expressway, and (2) not later than 30 days after the con…
March 2026
Authorization to terminate an existing intergovernmental Project Specific Agreement with Dallas County and enter a new agreement designating the City as lead agency to administer construction for Cockrell Hill Road from La Reunion to Singleton Boulevard, at no cost to the City.
…ead agency to administer construction for Cockrell Hill Road from La Reunion to Singleton Boulevard - Financing: No cost consideration to the City *In alignment with Infrastruc…
Authorize a Project Specific Agreement with Dallas County designating the City of Dallas as lead agency to administer construction on Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard, with appropriations and reimbursement funds up to $4,799,895.91 in the Capital Projects Reimbursement Fund.
…cy to administer construction for Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard; (2) the establishment of appropriations in an amount not to exceed $4,799,895.…
Authorization of a construction services contract with Urban Infraconstruction, LLC — the lowest of five bidders — to build Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard, not to exceed $20,330,000 financed across seven capital and bond funds.
Authorize a construction services contract for the construction of Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard - Urban Infraconstruction, LLC, lowest responsible bidder of five -
Authorizes a Project Specific Agreement with Dallas County designating the City of Dallas as lead agency to administer construction of Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard, with up to $4,796,229.40 in county reimbursement funds to be received and appropriated.
…cy to administer construction for Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard; (2) to establish appropriations in an amount not to exceed $4,796,22…
Construction services contract with Urban Infraconstruction, LLC, the lowest responsible bidder among five, for construction of Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard, not to exceed $20,330,000, financed across four city funds including 2024B Certificates of Obligation.
Authorize a construction services contract for the construction of Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard - Urban Infraconstruction, LLC, lowest responsible bidder of five -
February 2026
The city is authorizing payment to Union Pacific Railroad Company for rights to construct and maintain a grade-separated overpass on Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard, pursuant to a 2017 agreement (Resolution No. 17-1165), not to exceed $238,632 financed by the 2024B Certificates of Obligation Fund.
…within the UPRR right-of-way for Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard, to include payment to UPRR for the right to construct, maintain, and repair a…